An AQL sampling plan is only half of what ISO 2859-1 and ANSI/ASQ Z1.4 describe. The other half is a set of switching rules that change how hard you inspect, based on the supplier's recent results. Without them, the AQL tables give much weaker protection than the standards intend: the rules are what make a supplier with a bad run pay for it in tighter inspection.
The ISO rules below are in clause 9 of ISO 2859-1. Its third edition, ISO 2859-1:2026, replaced the 1999 edition in January 2026. Its list of main changes covers skip-lot and the OC curves, not the normal, tightened and reduced rules.
The three severities
| Severity | When | Effect |
|---|---|---|
| Normal | At the start, and the default. | The standard plan for the code letter and AQL. |
| Tightened | After poor results. | Same sample size (usually), lower accept numbers. |
| Reduced | After a sustained run of good lots, if approved. | Smaller sample, often 40% of normal. |
Normal to tightened
Switch to tightened when 2 out of 5 or fewer consecutive lots are rejected on original inspection (resubmitted lots don't count). This rule is the same in ISO 2859-1 and Z1.4.
Tightened to normal
Return to normal once 5 consecutive lots are accepted on tightened inspection.
Discontinuing inspection
If the cumulative number of lots rejected while on tightened inspection reaches 5, stop accepting product under the plan. Restart only after the supplier has corrected the cause, and then on tightened inspection. In practice this is where a supplier corrective action request (SCAR) comes in.
Normal to reduced
Reduced inspection is optional and needs the responsible authority's approval. Production must be steady, and the supplier must have a sustained record of accepted lots. The two standards measure that record differently:
- ANSI/ASQ Z1.4: the preceding 10 lots on normal inspection were all accepted. Since the 2003 edition, also checking the total number of defectives in those lots against the limit numbers (Table VIII) is optional.
- ISO 2859-1: a switching score. It starts at 0 on normal inspection and is updated after each lot. Where the accept number is 2 or more, add 3 if the lot would also have been accepted at the next tighter AQL, otherwise reset to 0. Where it is 0 or 1, add 2 if the lot is accepted, otherwise reset to 0. Switch to reduced when the score reaches 30.
Reduced to normal
Go back to normal as soon as a lot is rejected, production becomes irregular or delayed, or other conditions warrant it. The Z1.4 reduced plans have a gap between the accept and reject numbers. A result inside the gap is accepted, but inspection returns to normal. ISO 2859-1 has used reduced plans without that gap since its 1999 edition.
ISO 2859-1:2026 adds skip-lot to the switching rules. With the responsible authority's approval, a part with consistently good quality can move from normal or reduced inspection to skip-lot, and it returns to normal inspection when skip-lot ends (9.3.5, 9.3.6, 9.5). ISO 2859-3 is the dedicated skip-lot standard.
Why teams skip the rules, and why that's a problem
On paper, switching is simple. In practice it means tracking every part and supplier combination through a rolling history of lots, which is why many receiving teams quietly stay on normal inspection forever. That wastes inspection effort on good suppliers and lets poor ones off lightly. Auditors also notice when a procedure cites the switching rules but the records show they were never applied.