Skip-lot inspection means fully inspecting only a random fraction of incoming lots, such as 1 in 3, for a part with a proven record, and accepting the rest on the strength of that record. It is the biggest lever a receiving inspection team has. A good supplier's routine shipments stop queuing at the dock, and inspectors spend their time on new parts, new suppliers and problem parts.
Skip-lot is defined in ISO 2859-3:2005, which works alongside the ISO 2859-1 AQL tables (ANSI/ASQ S1 is a related US standard). It is a disciplined procedure, not a favor to trusted suppliers: qualification, frequency and the rules for falling back to full inspection are all specified. The clause numbers below are from ISO 2859-3:2005. ISO 2859-1:2026 also added a skip-lot procedure of its own (clause 9.5); if your procedure cites that edition for skip-lot, check its clauses too.
What can go on skip-lot
Both the supplier and the part have to qualify (clause 4.1), and the responsible authority approves each one after an assessment.
- The supplier (5.1) has a documented system for controlling quality and design changes, inspects and records every lot, can detect and correct shifts in quality, and has had no change that might hurt quality.
- The part (5.2.1) has a stable design and no critical classes of nonconformity.
- It is inspected at general level I, II or III with an AQL of 0.025% or more.
- It was on normal or reduced inspection throughout the qualification period. Any time on tightened inspection makes it ineligible.
- Production has been essentially continuous: by default for at least 6 months, with at least one lot a month.
- Quality has been at the AQL or better for an agreed stability period, 6 months by default.
Qualifying a part
A part qualifies (5.2.2) when the preceding 10 or more consecutive lots were accepted on original inspection (resubmitted lots don't count) and its qualification score reaches 50 within 20 consecutive lots. If qualification takes longer than 20 lots, the score is recalculated over the last 20.
The score (5.3) rewards lots that pass with a margin. For single sampling on normal inspection:
| Plan | Points for an accepted lot |
|---|---|
| Ac 3 or more | 5 if it would still pass with the AQL two steps tighter, 3 if one step tighter |
| Ac = 2 | 5 with no nonconforming items in the sample, 3 with one |
| Ac = 1 | 5 with no nonconforming items in the sample, 1 with one |
| Ac = 0 | 3 |
Any other result, including a rejected lot, resets the score to zero. On reduced inspection the 5s become 3s and the 3s become 1s, so qualifying takes at least 17 lots. The score also resets to zero on any switch between normal, reduced and tightened except normal to reduced, on any change of state, and on any frequency change (5.3.6).
How often to inspect
The initial frequency (6.2) depends on how quickly the part reached the score of 50. That number of lots isn't something you choose: it measures how good the lots were. Every lot is inspected until the score reaches 50, and lots that pass with a wide margin get there in fewer lots:
| Lots it took to qualify | Initial frequency |
|---|---|
| 10 to 11 | 1 in 4 lots inspected |
| 12 to 14 | 1 in 3 |
| 15 to 20 | 1 in 2 |
For example, on normal inspection a part whose lots all pass with a wide margin earns 5 points a lot and reaches 50 at the 10-lot minimum, so it starts at 1 in 4. A part on a plan with Ac = 0 earns 3 points a lot and needs 17 lots, so it starts at 1 in 2. Taking longer shows the lots had less margin, so skip-lot starts more cautiously.
The frequencies used on skip-lot are 1 in 2, 1 in 3, 1 in 4 and 1 in 5. Which lots get inspected is decided by a random draw, not a fixed pattern: if the selection is predictable, a supplier could time a bad lot. The frequency drops one step, to as little as 1 in 5 (6.3), when all of these hold:
- 10 or more consecutive lots have been accepted on skip-lot since qualification, the last frequency change or requalification.
- The score reaches 50 within 20 consecutive lots.
- The responsible authority approves the change.
What interrupts or ends skip-lot
- Interruption (6.5): an inspected lot is not accepted, or is accepted but resets the score to zero. Every lot is then inspected (lot by lot) while the part requalifies.
- Requalification (6.6): 4 to 6 consecutive lots accepted and a score of 18 or more within 6 lots. Skip-lot then resumes one step more often than before, for example 1 in 3 instead of 1 in 4.
- Disqualification (6.7): requalification doesn't succeed within 6 lots. The part leaves skip-lot, goes back to lot-by-lot inspection under ISO 2859-1, and has to qualify again from the start.
- Conditions lapse (4.1): skip-lot can only continue while both the supplier and the part still meet the qualification requirements, for example no design change and no break in continuous production. The responsible authority verifies both at an agreed interval (5.1.3, 5.2.4).
Records auditors expect
- The skip-lot procedure and the approval of each part by the responsible authority.
- Which lots were skipped and which were inspected, and evidence that the selection was random.
- The qualification score history and every frequency change, interruption and requalification.
- Under AS9100, the statistical justification for the sampling plan (8.5.1 c) 2)).
Skip-lot is not ship-to-stock with no checks. Lots that skip inspection still get receiving checks: correct part and revision, quantity, packaging and paperwork such as certificates of conformance.